Shingara Sands is a multi-dwelling complex consisting of 300 units, grouped into stacks of 4, 6 & 8 units per block, plus Body Corporate Offices, Guard House, and Club House that required Fibre reticulation.

Existing 110mm feeder sleeves were used for Fibre reticulation routes. Some repairs to existing infrastructure were caried out to the highest quality.

38 Dome Joints have been installed on feeder routes. Distribution Boxes were installed at all Blocks for unit drop Fibre termination.

Street Cabinet was placed at Guard House for Fibre aggregation points and splitter installation.

Occupational Health & Safety Audit:

A score of 97% achieved throughout the project. Audit completed by Fibre Network Operator.

  • Prev
  • Next
  • Category

    Past Projects
  • Mated Connector Loss

    0.5 dB
  • Splice Attenuation

    0.03 dB
  • Cable Attenuation at 1310nm

    0.35 dB/km
  • Cable Attenuation at 1490nm

    0.22 dB/km
  • Cable Attenuation at 1550nm

    0.19 dB/km